Visitors to the Lismore Recycling & Recovery Centre (LRRC) will soon benefit from safer access, improved traffic flow and upgraded facilities, with a major improvement program to begin next month.

The works will be delivered in stages from August 2026 to February 2027 and include a new western sediment basin to capture and temporarily store stormwater runoff, upgraded internal roads and dedicated heavy vehicle routes, improved drainage, a new roundabout and upgrades to the popular Revolve Shop.

Roads damaged during the 2022 flood response will also be repaired.

As part of the project, the Revolve Shop will temporarily close for about 10 weeks from October to allow parking and access improvements within the precinct.

The upgrades form part of Council’s long-term investment in Lismore’s waste and resource recovery network. As the community grows and expectations around recycling, reuse and sustainability continue to evolve, Council is investing in infrastructure that will help residents recover more valuable resources and reduce the amount of residual waste sent to landfill.

The Revolve Shop diverts thousands of items from landfill each year, giving everyday goods a second life. It remains a valued community destination for affordable, pre-loved items and highlights the important role resource recovery plays in Lismore’s future.

Council acknowledges the temporary closure may cause some inconvenience and thanks customers for their patience while the works are carried out.

Lismore City Mayor Steve Krieg said the project supports Council’s long-term vision for waste management while delivering practical benefits for the community.

“The LRRC is one of Council’s busiest community facilities, and these works will make it safer, easier to use and better equipped to serve the community for years to come,” Krieg said.

“These important improvements are about more than today’s customer experience. They’re part of how we are preparing Lismore for the future.”

“Customers will benefit from better access, additional parking and improved traffic flow, while dedicated haul roads will separate heavy vehicles from public areas, creating a safer environment across the site.”

“Across Australia we’re seeing future waste planning become a significant challenge for local governments. By investing now we’re making sure Lismore is ready for that future.”

The LRRC will remain open throughout construction wherever possible. Customers may, however, experience temporary traffic changes, altered access arrangements and short-term diversions while the works are underway.

Council will provide advance notice of any significant disruptions and keep the community informed through its website, social media channels and on-site signage.

The upgrades are jointly funded by the Australian and NSW governments under the Disaster Recovery Funding Arrangements and Infrastructure Betterment programs.

For more information about waste and recycling services and Council’s plans for Lismore’s future resource recovery system, visit lismore.nsw.gov.au.